Posts Tagged ‘shelter forum

CONSTRUCTION OF A TOILET GHETTO KIAMAIKO TOILET

leave a comment »

Purpose of the project:-Improve health standard

Project information

Location

Huruma

Implementing agency

CDF

Project initiation

CDF

Estimated cost                                                           Project cost

        Remarks

 1,500,000                                                    Amount allocated:2006/2007-kshs. 800,000

Amount spent:

800,000

Year of funding

2006/2007

Status of the project

Complete and in use
Accountability standards

Quality

BAD

Accountability

Vital document not accessible

Status of public participation

Low citizen participation since the community was not involved in the implementation of the project

Usage/utility

In use but poor quality

NB: the information in this report was drawn from the Starehe CDF website

Observations

  • Cheap labor and misuse of materials
  • Poor work
  • Misuse of materials
  • This is an irrelevant project since there were two toilets which were built by the former MP Maina Kamanda and they were not completed.

Recommendations

  • The community/ beneficiaries should be fully involved in the implementation of the project
  • A project committee should be formed to supervise and monitor the implementation process
  • In case of misuse of fund the area MP should be arrested and prosecuted and the contractor black listed

link to the map

 

Pictures

Written by Community watch dogs starehe.

February 26, 2012 at 11:55 am

TOILET CONSTRUCTION NDURURUNO PRIMARY SCHOOL

leave a comment »

Purpose of the project:-Improve health standards

Project information

Location

Huruma

Implementing agency

CDF

Project initiation

CDF

Estimated cost                                          Project cost

Remarks

 500,000                                                         Amount allocated:2003/2004-kshs. 500,000

Amount spent:

 498,000

Year of funding

2003/2004

Status of the project

Complete and in use
Accountability standards

Quality

Poor

Accountability

Vital document accessible

Status of public participation

Low citizen participation since the community was not involved in the implementation of the project

Usage/utility

Improve health standards

NB: The information in this report was drawn from the Starehe CDF website

observations

  • shoddy job
  • cheap labor
  • unqualified contractor

recommendations

  • A project sustainability committee should be established to ensure proper maintenance of the project

link to the map

Pictures

Written by Community watch dogs starehe.

February 4, 2012 at 12:12 pm

CONSTRUCTION OF A SOCIAL HALL AND A NURSERY SCHOOL HURUMA SOCIAL HALL

leave a comment »

Purpose of the project:-Improve social activities

Project information

Location

Huruma

Implementing agency

CDF

Project initiation

CDF

Estimated cost                                      Project cost

Remarks

10,000,000                                                          Amount allocated:2005/2006-kshs. 3,000,0002006/2007-kshs. 2,500,0002007/2008-kshs. 4,000,000

 

Amount spent:

6,094,780

Year of funding

2005/20062006/20072007/2008 

Status of the project

Complete and in use
Accountability standards

Quality

Good

Accountability

Vital document accessible

Status of public participation

Low citizen participation since the community was not involved in the implementation of the project

Usage/utility

In use

NB: The information in this report was drawn from the Starehe CDF website

observation

  • Good finish work

link to the map

 

Pictures

Written by Community watch dogs starehe.

February 4, 2012 at 12:03 pm

CONSTRUCTION OF POLICE POST HURUMA POLICE POST

with one comment

Purpose of the project:-Improve security

Project information

Location

Huruma

Implementing agency

CDF

Project initiation

CDF

Estimated cost   Project cost

 1,500,000                                                            Amount allocated:2004/2005-kshs.1,500,0002005/2006-kshs.500,000

Amount spent:

2,000,000

Year of funding

2004/20052005/2006

Status of the project

Complete and in use
Accountability standards

Quality

Good

Accountability

Vital document accessible

Status of public participation

Both public and CDF officials were involved in this process

Usage/utility

in use

NB: the information in this report was drawn from the Starehe CDF website

obsevation

  • shoddy job
  • poor workmanship

link to the map

 

Pictures

Written by Community watch dogs starehe.

February 4, 2012 at 11:57 am

PROJECT: CONSTRUCTION OF FOOT BRIDGE CONNECTING THAYU AND MASHIMONI

leave a comment »

Project information

Location

Mathare

Implementing agency

LASDAP

Project initiation

Area councilor(swadi)

Cost of the project

Amount allocated: not availed

Amount spent: records availed

Year of funding

2009-2010

Status of the project

Complete but poor

Quality

Poor

Accountability standards

Accountability

Low level of accountability and transparency since no records were available and no interaction with the beneficiaries

Status of public participation

There is Low citizen participation with allegations that the councilor does what he deems fit for the community without consulting

Usage/utility

In use

Source:   Beneficiaries

Observations

The project is complete but the community is afraid since the foot bridge collapse during the construction                                                                                                                                                                                                        Recommendations

  • City engineer should inspect why the bridge collapsed during constructions
  • The community/ beneficiaries should be fully involved in the implementation of the project
  • In case of misuse of fund the area councilor should be arrested and prosecuted and the contractor black listed and return the stolen fund

Written by Community watch dogs starehe.

January 30, 2012 at 12:04 pm

ROAD UPGRADING PROJECT MABATINI, MASHIMONI

leave a comment »

Project information

Location

Mathare

Implementing agency

LASDAP

Project initiation

Area councilor(swadi)

Cost of the project

Amount allocated: not availed

Amount spent: records availed

Year of funding

2009-2010

Status of the project

Still under construction but poor standard

Quality

Poor

Accountability standards

Accountability

Low level of accountability and transparency since no records were available and no interaction with the beneficiaries

Status of public participation

There is Low citizen participation with allegations that the councilor does what he deems fit for the community without consulting

Usage/utility

Not In use

Source:   Beneficiaries and lasdap website

Observations

Poor foundation, cheap labor, unqualified contractor, shoddy job

Recommendations

  • LASDAP officials should explain why the project is incomplete
  • The community/ beneficiaries should be fully involved in the implementation of the project
  • A project committee should be formed to supervise and monitor the implementation process
  • In case of misuse of fund the area councilor should be arrested and prosecuted and the contractor black listed

link to the map

 

Written by Community watch dogs starehe.