Cdf and Latif Starehe

social accountabilty for better and brighter future in starehe

Posts Tagged ‘map kibera trust

CONSTRUCTION OF A TOILET KOSOVO TOILET

leave a comment »

Purpose of the project:-Improve health standard

Project information

Location

Mathare

Implementing agency

CDF

Project initiation

CDF

        Estimated cost            Project cost

Remarks

1,500,000                                                    Amount allocated:2006/2007-kshs. 800,000Kshs 300,000 reallocated from st Teresa girls project

Amount spent:

1,100,000

Year of funding

2006/2007

Status of the project

not in use
Accountability standards

Quality

Poor

Accountability

Vital document not accessible

Status of public participation

Community did not participat in all stages of implementation

Usage/utility

not in use

NB: the information in this report was drawn from the Starehe CDF website

Observation

  • Shoddy work
  • Poor workman ship
  • Misuse of material by the contractor

Recommendation

  • The contractor should be investigated
  • In case of misuse of fund he/she should be arrested and prosecuted
  • The community should be fully involved since they were only involved during initiation.

link to the map

 

Written by Community watch dogs starehe.

March 13, 2012 at 2:36 pm

CONSTRUCTION OF DANIEL COMBONI ROAD HURUMA

leave a comment »

Purpose of the project:-Improve transportation

     Project information

Location

Huruma

Implementing agency

CDF

Project initiation

CDF

          Estimated cost               Project cost

                                             Remarks

                                                   Amount allocated:

Amount spent:

Not specified

Year of funding

2010-2011

Status of the project

Complete and in use
Accountability standards

Quality

Good

Accountability

Vital document accessible

Status of public participation

Community participated in all stages of implementation

Usage/utility

In use

NB: the information in this report was drawn from the COMMUNITY

Observation

Good work

Proper finish work

Recommendations

  • Records should be availed to determine how much was used was allocated to this project
  • Accountability and transparency board should be installed

link to the map

Pictures

Written by Community watch dogs starehe.

March 13, 2012 at 2:08 pm

CONSTRUCTION OF TOILET MASHINDE GROUNDS HURUMA

leave a comment »

Purpose of the project:-Improve learning condition

Project information

Location

Huruma

Implementing agency

CDF

Project initiation

CDF

        Estimated cost            project cost

  Remarks

                                                    Amount allocated:Unknown

Amount spent:

Unknown

Year of funding

Unknown

Status of the project

Complete but not in use
Accountability standards

Quality

Poor

Accountability

Vital document accessible

Status of public participation

Low citizen participation since the community was not involved in the implementation of the project

Usage/utility

Not in use

NB: the information in this report was drawn from the Starehe CDF website

shoddy job

poor workmanship

Recommendations

  • The CDFC should purchase the missing equipments for the facility to achieve its common objective
  • Project should be completed in good time to avoid delay and misuse of more funds
  • The CDFC should inform the beneficiaries on when the project will be completed
  • A financial audit should be urgently done as a first in recovery of any lost funds
  • Records should be availed to determine how much was allocated to this project.
  • Transparency and accountability board should be installed

link to the map

 

Pictures

Written by Community watch dogs starehe.

March 13, 2012 at 1:59 pm