HURUMA STALLS

leave a comment »

Purpose of the project:-improve business

Project information

Location

Huruma

Implementing agency

CDF

Project initiation

CDF

           Estimated cost             Project cost

                                                   Remarks

3,529,655.58                                                Amount allocated:3,529,655.58

Amount spent:

 Not specified

Year of funding

Status of the project

Complete and not in use
Accountability standards

Quality

 Fair

Accountability

Vital document accessible

Status of public participation

Low citizen participation since the community was not involved in the implementation of the project

Usage/utility

Not in use

NB: the information in this report was drawn from the Starehe CDF website

Observations

The stall have not yet been opened

No electricity

Cheap and shoddy job

Cheap labour

Poor project location

RECOMMENDATIONS

  • A financial audit should be urgently done as a first in recovery of any lost funds
  • The local community should be involved in implementation and monitoring the progress of the project.
  • In case of misuse of funds the project contractor should be arrested and prosecuted

link to the map

 

Written by Community watch dogs starehe.