Posts Tagged ‘Inuka trust’
SUPPLY OF PLASTIC CHAIRS DAIMA PRIMARY SCHOOL
Purpose of the project was to improve learning condition
| Project information |
Location |
Huruma |
|
Implementing agency |
CDF | |
|
Project initiation |
CDF | |
|
Estimated cost Project cost Remarks |
439,000,000 Amount allocated:2009/2010-kshs. | |
|
Amount spent: |
439,000,000 | |
|
Year of funding |
Not specified | |
|
Status of the project |
||
| Accountability standards |
Quality |
|
|
Accountability |
Vital document accessible | |
|
Status of public participation |
Community participated in all stages of implementation | |
|
Usage/utility |
In use |
NB: the information in this report was drawn from the Starehe CDF website
Observation
Good
Recommendations
- Plastic chairs are not durable next time cdf official should supply the school with metallic chairs.
- The school committee should demand to know how much the plastic chairs costed
pictures
CONSTRUCTION OF A TOILET KOSOVO TOILET
Purpose of the project:-Improve health standard
| Project information |
Location |
Mathare |
|
Implementing agency |
CDF | |
|
Project initiation |
CDF | |
|
Estimated cost Project cost Remarks |
1,500,000 Amount allocated:2006/2007-kshs. 800,000Kshs 300,000 reallocated from st Teresa girls project | |
|
Amount spent: |
1,100,000 | |
|
Year of funding |
2006/2007 | |
|
Status of the project |
not in use | |
| Accountability standards |
Quality |
Poor |
|
Accountability |
Vital document not accessible | |
|
Status of public participation |
Community did not participat in all stages of implementation | |
|
Usage/utility |
not in use |
NB: the information in this report was drawn from the Starehe CDF website
Observation
- Shoddy work
- Poor workman ship
- Misuse of material by the contractor
Recommendation
- The contractor should be investigated
- In case of misuse of fund he/she should be arrested and prosecuted
- The community should be fully involved since they were only involved during initiation.
CONSTRUCTION OF DANIEL COMBONI ROAD HURUMA
Purpose of the project:-Improve transportation
| Project information |
Location |
Huruma |
|
Implementing agency |
CDF | |
|
Project initiation |
CDF | |
|
Estimated cost Project cost Remarks |
Amount allocated: | |
|
Amount spent: |
Not specified | |
|
Year of funding |
2010-2011 | |
|
Status of the project |
Complete and in use | |
| Accountability standards |
Quality |
Good |
|
Accountability |
Vital document accessible | |
|
Status of public participation |
Community participated in all stages of implementation | |
|
Usage/utility |
In use |
NB: the information in this report was drawn from the COMMUNITY
Observation
Good work
Proper finish work
Recommendations
- Records should be availed to determine how much was used was allocated to this project
- Accountability and transparency board should be installed
Pictures
CONSTRUCTION OF TOILET MASHINDE GROUNDS HURUMA
Purpose of the project:-Improve learning condition
| Project information |
Location |
Huruma |
|
Implementing agency |
CDF | |
|
Project initiation |
CDF | |
|
Estimated cost project cost Remarks |
Amount allocated:Unknown | |
|
Amount spent: |
Unknown | |
|
Year of funding |
Unknown | |
|
Status of the project |
Complete but not in use | |
| Accountability standards |
Quality |
Poor |
|
Accountability |
Vital document accessible | |
|
Status of public participation |
Low citizen participation since the community was not involved in the implementation of the project | |
|
Usage/utility |
Not in use |
NB: the information in this report was drawn from the Starehe CDF website
shoddy job
poor workmanship
Recommendations
- The CDFC should purchase the missing equipments for the facility to achieve its common objective
- Project should be completed in good time to avoid delay and misuse of more funds
- The CDFC should inform the beneficiaries on when the project will be completed
- A financial audit should be urgently done as a first in recovery of any lost funds
- Records should be availed to determine how much was allocated to this project.
- Transparency and accountability board should be installed
Pictures
CONSTRUCTION OF A TOILET GHETTO KIAMAIKO TOILET
Purpose of the project:-Improve health standard
| Project information |
Location |
Huruma |
|
Implementing agency |
CDF | |
|
Project initiation |
CDF | |
|
Estimated cost Project cost Remarks |
1,500,000 Amount allocated:2006/2007-kshs. 800,000 | |
|
Amount spent: |
800,000 | |
|
Year of funding |
2006/2007 | |
|
Status of the project |
Complete and in use | |
| Accountability standards |
Quality |
BAD |
|
Accountability |
Vital document not accessible | |
|
Status of public participation |
Low citizen participation since the community was not involved in the implementation of the project | |
|
Usage/utility |
In use but poor quality |
NB: the information in this report was drawn from the Starehe CDF website
Observations
- Cheap labor and misuse of materials
- Poor work
- Misuse of materials
- This is an irrelevant project since there were two toilets which were built by the former MP Maina Kamanda and they were not completed.
Recommendations
- The community/ beneficiaries should be fully involved in the implementation of the project
- A project committee should be formed to supervise and monitor the implementation process
- In case of misuse of fund the area MP should be arrested and prosecuted and the contractor black listed
Pictures